What does 'crash time' refer to in project management?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Prepare for the NCEES Fundamentals of Engineering (FE) Civil Exam with multiple choice questions, hints, and detailed explanations. Maximize your study efficiency and ace your exam!

'Crash time' in project management specifically refers to the shortest possible time required to complete an activity after taking steps to expedite it, typically involving allocating additional resources or increasing work hours. This concept is crucial when a project needs to be completed sooner than originally planned, and it often involves analyzing the potential costs and impacts of speeding up project activities.

In contrast to the other options, which address different aspects of project management, crash time is distinct because it focuses solely on the reduction of time for specific tasks within a project. The time between project planning and execution relates more to scheduling and process phases, while the average time to finish project activities speaks to a broader view of project timelines rather than the focused reduction of one task. Similarly, the duration needed to analyze risks pertains to the assessment and management of uncertainties rather than the direct acceleration of project tasks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy